Project - Cowards Creek Slope Paving & Bank Repair

G250148 – Cowards Creek Slope Paving & Bank Repair

Location: Cowards Creek near Del Monte Drive / Cowards Creek Crossing Subdivision
Project Type: Bank Stabilization & Slope Paving
Status: Construction Underway

Project Overview

GCCDD is completing a significant bank stabilization and slope paving project along Cowards Creek near Del Monte Drive and the Cowards Creek Crossing Subdivision.

The project, identified as G250148, began after District personnel discovered a major slope failure along the creek bank in 2025. While erosion and bank repairs are a regular part of maintaining approximately 72 miles of streams and drainage facilities throughout the District, this location presented an especially complex challenge: eight natural gas pipelines cross beneath the project area.

Some of these lines are located only approximately three feet below the surface, requiring careful coordination and a repair designed not only to restore the failed bank, but also to provide long-term protection for the infrastructure beneath it.

Discovery of the Bank Failure

District personnel identified the slope failure during 2025 and began evaluating the extent of the damage and the appropriate method of repair.

The failure affected a portion of the Cowards Creek bank near Del Monte Drive stretching over 500 feet.

Because multiple pipelines cross the District's drainage facility at this location, a conventional bank repair could not simply move forward without additional investigation, engineering, and coordination.

Protecting the integrity of the creek while avoiding damage to the pipelines became a central consideration in developing the project.

Engineering a Solution

Following discovery of the failure, the District began developing a repair plan that would stabilize the damaged bank and provide a more durable surface in this particularly sensitive section of Cowards Creek.

The selected approach includes slope paving a portion of the repair, which provides a hardened and stabilized surface along the bank. At this location, the paving serves an additional purpose: helping protect the shallow pipeline crossings from future erosion that could otherwise reduce the amount of material covering the lines or potentially expose them.

Because the work occurs within the creek and involves modifications to the channel, the project also required coordination with the U.S. Army Corps of Engineers (USACE) and applicable federal permitting.

By March 2026, the project had advanced sufficiently for GCCDD's engineers to request that the proposed bank repair and slope paving installation be brought before the Board of Directors, while the necessary USACE permitting process moved forward.

Why This Repair Matters

Drainage infrastructure is interconnected with much more than the water you see flowing through a creek.

Roadways, bridges, utilities, pipelines, neighborhoods, and other infrastructure frequently cross or exist alongside the drainage system. When erosion or a slope failure occurs, the District must consider not only how to restore the creek bank, but also what infrastructure could be affected if that failure continues.

At G250148, the presence of eight pipeline crossings makes preventing continued erosion especially important.

The completed slope paving will help:
- Stabilize the failed section of the Cowards Creek bank;
- Reduce the potential for continued erosion at the repair location;
- Protect pipeline infrastructure crossing beneath the channel;
- Provide a more durable surface in an area with significant infrastructure constraints; and
- Reduce the likelihood that a localized bank failure develops into a larger and more costly problem.

Construction Underway

Following engineering, permitting, and project coordination, construction is now underway.

Crews are working carefully around the existing pipeline infrastructure while preparing and paving the affected slope. The work visible today represents the culmination of a process that began with identifying the failure in 2025 and continued through investigation, engineering, utility coordination, permitting, and ultimately construction.

The District will continue documenting the project as work progresses and will update this page with photographs and additional information through completion.

Project Timeline

2025
GCCDD identifies a major bank and slope failure along Cowards Creek near Del Monte Drive.

Late 2025 – Early 2026
The District and its engineers evaluate the failure, pipeline crossings, repair alternatives, and permitting requirements. Portions of the slope are repaired in a customary manner involving excavation, stabilization of soil and placement of riprap, and sloping to an erosion resistant 4:1 gradient.

March 2026
The proposed bank repair and slope paving portion of the project advances for Board consideration. Due to the location within Cowards Creek, USACE permitting is incorporated into the project process.

2026
Engineering, permitting, utility coordination, and pre-construction activities continue.

September 2026
Construction and slope paving are underway, with crews working around eight natural gas pipelines crossing the project area.

Next Step
Complete slope paving and stabilization work and document the finished repair.